Surveying, Water resources
Sustainable On-Site Power Derived from Gravity-Fed Water Flow
Challenges & highlights
Because of how water rights work in Colorado, the town needs to demonstrate continuous beneficial use of its full water right or risk losing it. As part of this project, the team expanded the collection system at the diversion point to capture as much water as the right allows. The system gives operators the ability to divert the full right consistently, which is what matters legally, while managing actual use based on treatment demand.
The hydro unit itself takes advantage of the significant elevation drop between the diversion point and the treatment facility. Water passes through the unit, spins a motor, and generates approximately 45 kilowatts per day. That output covers the basic electrical load of the treatment plant, offsetting one of the town’s highest per-facility energy costs.
The results
The project adds a source of renewable energy to the town’s infrastructure and helps Carbondale work toward its net-zero energy goals. The on-site generation eliminates the electrical costs of running the Nettle Creek facility under normal operating conditions. The collection system expansion also strengthens the town’s legal standing on a water right that has served the community for over a century, protecting a resource that supports Carbondale’s long-term water supply.
Elevation: 6,181 ft
Location: Carbondale, CO
Infrastructure that lasts
Whether you’re planning a new development, upgrading public infrastructure, or improving community systems, our team is ready to help bring your project from concept to completion.